Saudi Yanbu Phase III Project Unit 3 completes boiler blowpipe successfully

秒速飞艇2019-5-3 14:08:51

At 14:58 of May 2, 2019, Saudi Yanbu Phase III 5×660MW Oil-fired Project Unit 3 completed boiler blowpipe successfully.

The project adopted the two-stage blowpipe methods, that is the boiler superheater and the reheaterseparately blow in stages. The superheater mode is the step-down blowpipe, the reheater mode is the regulated blowpipe, and used the German VGB standard. Compared with Unit 2 boiler blowpipe, Unit 3 completed it earlier 7 days. The successful completion of Unit 3 boiler blowpipe lays a solid foundation for following synchronization work.